Wednesday, September 29, 2010

Haist Street Reconstruction Update


Whether you live on it or near it, you might be wondering about the Town’s progress on reconstructing Haist Street.

You will recall that Haist Street is being reconstructed from Canboro to Welland Road all in one year thanks to infrastructure stimulus funds from the Federal and Provincial governments. The Town had initially budgeted to undertake the work in stages over three years; instead we are able to invest 1/3 of the $5.7 million cost one-year only.

Since I had a couple of questions recently about the project’s financing, I want you to know that the Town is not incurring any debt for the project. Also, the project is well within budget and all contingencies are intact.

The contractor – Provincial Construction from Niagara Falls – has divided the project into two sections.

North of Pancake Lane (to Canboro Road), the contractor has already replaced the storm sewers and the watermain. Until mid-November, the contractor plans to attach water services and install new curbs and sidewalks. Staff expect that the base layer of asphalt will be paved in mid- to late-November.

Work in the section South of Pancake Lane (to Welland Road) is more complicated because the groundwater is so close to the surface. Provincial Construction has had to carry on extensive “dewatering” – pumping of groundwater out of the area – so that they can work underground. Staff expects the installation of storm sewers to be completed by mid-October, and the installation of the new watermain by the end of October. In this Southern half, curb and sidewalk work should take until the end of November and that base coat of asphalt should be paved in mid-December.

In the spring of 2011, Provincial Construction will pave the top-coat of asphalt, add sod and plant trees throughout both sections.

Staff meets with the contractor weekly to ensure the project continues to move along. And, while contingency plans are in place, this timeline is dependent on weather.

Finally, we are trying to be as proactive as possible on communication. For example, the Town's website contains biweekly updates. You can view the most recent update – Number 8 from September 21 – by scrolling down on the homepage of the Town’s website at www.pelham.ca. Staff also sent a letter to AK Wigg families on the first day of school about getting to and from school.

While the end is in sight, I sincerely appreciate the ongoing patience of residents living on and near Haist Street.